Liaoning Gas Pipeline Network
Liaoning Gas Pipeline Network is an operating gas transmission pipeline in China. The tracker lists 1 tracked segment, 68 km long and 0.82 bcm/y of capacity, starting up in 2018. It runs from Wafangdian First Station, Wangdian Village, Taiyang Street Office,Wafangdian to Xietun Station, Gaotun Village, Paoya Township, Wafangdian. It is owned by PetroChina Kunlun Gas Co Ltd.
Length
68 km
Capacity
0.82 bcm/y
0.6 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 324 mm (13 in)
Route
Liaoning Gas Pipeline Network runs from Wafangdian First Station, Wangdian Village, Taiyang Street Office,Wafangdian to Xietun Station, Gaotun Village, Paoya Township, Wafangdian. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Wafangdian First Station, Wangdian Village, Taiyang Street Office,Wafangdian
- To
- Xietun Station, Gaotun Village, Paoya Township, Wafangdian
- Start country
- China
- End country
- China
- Countries crossed
- China
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 67 km
- GEM pipeline ID
- P5966
- Start year
- 2018
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Wafangdian-Changxingdao Branch Gas Pipeline | Operating | Wafangdian First Station, Wangdian Village, Taiyang Street Office,Wafangdian → Xietun Station, Gaotun Village, Paoya Township, Wafangdian | 68 | 0.82 | 324 mm | 2018 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.