Gas transmission pipeline · Kozarac to Slobodnica
Omišalj-Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica LNG main evacuation pipeline
Omišalj-Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica LNG main evacuation pipeline is a proposed gas transmission pipeline in Croatia. The tracker lists 1 tracked segment, 128 km long and 3.29 bcm/y of capacity, starting up in 2030. It runs from Kozarac to Slobodnica. It is owned by Plinacro Ltd.
Length
128 km
Capacity
3.29 bcm/y
2.4 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 800 mm (31 in)
Route
Omišalj-Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica LNG main evacuation pipeline runs from Kozarac to Slobodnica. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Kozarac
- To
- Slobodnica
- Start country
- Croatia
- End country
- Croatia
- Countries crossed
- Croatia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 115 km
- GEM pipeline ID
- P2191
- Start year
- 2030
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Kozarac-Slobodnica | Proposed | Kozarac → Slobodnica | 128 | 3.29 | 800 mm | 2030 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Plinacro Ltd100%
Parent companies
- Plinacro doo100%