Gas transmission pipeline · Payra Port to Gopalgonj
Payra-Barishal-Gopalganj Gas Transmission Pipeline
Payra-Barishal-Gopalganj Gas Transmission Pipeline is a cancelled gas transmission pipeline in Bangladesh. The tracker lists 1 tracked segment, 153 km long, starting up in 2025. It runs from Payra Port to Gopalgonj.
Length
153 km
Capacity
Not reported
Segments tracked
1
Largest diameter 1067 mm (42 in)
Route
Payra-Barishal-Gopalganj Gas Transmission Pipeline runs from Payra Port to Gopalgonj. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Payra Port
- To
- Gopalgonj
- Start country
- Bangladesh
- End country
- Bangladesh
- Countries crossed
- Bangladesh
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 150 km
- GEM pipeline ID
- P6847
- Start year
- 2025
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Cancelled | Payra Port → Gopalgonj | 153 | Not reported | 1067 mm | 2025 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Payra LNG Terminal | Bangladesh | Import | Cancelled | 1.1 km | route proximity |
| Payra FSRU | Bangladesh | Import | Cancelled | 1.5 km | route proximity |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Ownership is not reported for this pipeline.