Gas transmission pipeline · Guangdong to Shiting Town

West-East Gas Pipeline 3

West-East Gas Pipeline 3 is an under construction gas transmission pipeline in China. The tracker lists 1 tracked segment, 209 km long and 5.8 bcm/y of capacity, starting up in 2025. It runs from Guangdong to Shiting Town. It is owned by West to East Gas Transmission Branch of National Petroleum Pipeline Network Group Co Ltd.

Length

209 km

Capacity

5.8 bcm/y

4.3 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 813 mm (32 in)

Route

West-East Gas Pipeline 3 runs from Guangdong to Shiting Town. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Guangdong
To
Shiting Town
Start country
China
End country
China
Countries crossed
China
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
210 km
GEM pipeline ID
P4930
Start year
2025
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Fujian–Guangdong Branch Phase II (Chaozhou–Zhangzhou)Under constructionGuangdong → Shiting Town2095.8813 mm2025GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.