LNG Chain

Gas transmission pipeline · Gazimammad to Abadan

Hajiqabul–Astara–Abadan Gas Pipeline

Hajiqabul–Astara–Abadan Gas Pipeline is an operating gas transmission pipeline crossing Azerbaijan, Iran. The tracker lists 1 tracked segment, 1,475 km long and 10 bcm/y of capacity, starting up in 1970. It runs from Gazimammad to Abadan. It is owned by National Iranian Oil Refining and Distribution Co and SOCAR.

Length

1,475 km

Capacity

10 bcm/y

7.4 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1020 mm (40 in)

Route

Hajiqabul–Astara–Abadan Gas Pipeline runs from Gazimammad to Abadan. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Gazimammad
To
Abadan
Start country
Azerbaijan
End country
Iran
Countries crossed
Azerbaijan, Iran
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
1,292 km
GEM pipeline ID
P0748
Start year
1970
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingGazimammad → Abadan1,475101020 mm1970GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.