LNG Chain

Gas transmission pipeline · Hermanowice to Jarosław

Hermanowice-Jaroslaw Pipeline

Hermanowice-Jaroslaw Pipeline is a proposed gas transmission pipeline in Poland. The tracker lists 1 tracked segment, 39 km long, starting up in 2029. It runs from Hermanowice to Jarosław. It is owned by Gaz-System.

Length

39 km

Capacity

Not reported

Segments tracked

1

Largest diameter 700 mm (28 in)

Route

Hermanowice-Jaroslaw Pipeline runs from Hermanowice to Jarosław. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Hermanowice
To
Jarosław
Start country
Poland
End country
Poland
Countries crossed
Poland
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
34 km
GEM pipeline ID
P1349
Start year
2029
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineProposedHermanowice → Jarosław39Not reported700 mm2029GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.