LNG Chain

Gas transmission pipeline · Katy to Port Arthur

Trident Gas Pipeline

Trident Gas Pipeline is a proposed gas transmission pipeline in United States. The tracker lists 1 tracked segment, 348 km long and 15.33 bcm/y of capacity, starting up in 2027. It runs from Katy to Port Arthur. It is owned by Kinder Morgan Inc.

Length

348 km

Capacity

15.3 bcm/y

11.3 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1067 mm (42 in)

Route

Trident Gas Pipeline runs from Katy to Port Arthur. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Katy
To
Port Arthur
Start country
United States
End country
United States
Countries crossed
United States
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
347 km
GEM pipeline ID
P7779
Start year
2027
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineProposedKaty → Port Arthur34815.31067 mm2027GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Golden Pass LNG TerminalUnited StatesExportOperating1.5 kmroute proximity
Port Arthur LNG TerminalUnited StatesExportUnder construction1.5 kmroute proximity
Sabine Pass LNG TerminalUnited StatesExportOperating5.9 kmroute proximity
Alturas LNG TerminalUnited StatesExportCancelled8 kmroute proximity
Phillips 66 Beamont Oil TerminalUnited StatesExportOperating16.4 kmroute proximity
Beacon Port LNG TerminalUnited StatesImportCancelled22.8 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.