LNG Chain

Import terminal · Poland

Polish Baltic Sea Coast FSRU

Polish Baltic Sea Coast FSRU is an under construction LNG import terminal (floating storage and regasification unit (FSRU)) in Poland. The tracker lists 2 tracked units with 4.49 Mtpa under construction, 3.31 Mtpa proposed. It is owned by Operator Gazociagow Przesylowych GAZ-SYSTEM SP zoo.

Operating

no units operating

Under construction

4.49 Mtpa

6.1 bcm/y · 1 unit

Proposed

3.31 Mtpa

4.5 bcm/y · 1 unit

At a glance

Country
Poland
State / province
Not reported
Region
Not reported
Import / export
Import
Onshore / floating
FSRU
Status (rolled up)
Under construction
Trains / phases tracked
2
Earliest start year
Not reported
Latest start year
Not reported
Coordinates
54.4247° N, 18.7358° E
GEM terminal ID
T100000130731
GEM wiki page
gem.wiki

Trains and phases

Each row is one unit as tracked by GEM. Ordered by start year, then proposal year.

UnitStatusCapacity (Mtpa)Capacity (bcm/y)StartProposedFIDOwner (as reported)
Not reportedUnder construction4.496.1Not reportedOperator Gazociagow Przesylowych GAZ-SYSTEM SP zoo [100%]
Unit Expansion (FSRU 2)Proposed3.314.5Not reportedOperator Gazociagow Przesylowych GAZ-SYSTEM SP zoo [100%]

Some units are reported by GEM in bcm/y; Mtpa is derived at 1 Mtpa = 1.36 bcm/y.

Capacity by status

StatusUnitsMtpabcm/y
Under construction14.496.1
Proposed13.314.5

Owners and operators

Stakes as reported by GEM per unit, merged across units. Percentages are omitted where GEM does not give them.

Location

Polish Baltic Sea Coast FSRU at 54.4247° N, 18.7358° E, with 7 tracked gas pipelines passing within 25 km.

Loads about 250 kB of map code and the country outline file.

Coordinates
54.4247° N, 18.7358° E
Coordinate accuracy (GEM)
approximate
Open in OpenStreetMap
View on map

Connected gas pipelines

Tracked pipelines whose route passes within 25 km of this terminal, or whose name matches it. Proximity is not proof of a physical connection.

PipelineStatusLengthCapacityDistanceMatched by
Goleniow–Gdynia Gas PipelineOperating278 km10.4 kmroute proximity
Wloclawek–Gdynia Gas PipelineOperating200 km10.7 kmroute proximity
Baltic Gas InterconnectorCancelled200 km3 bcm/yname match
Baltic Pipe ProjectOperating613 km10 bcm/yname match
Baltic Pipe ProjectOperating122 kmname match
Baltic Pipe ProjectOperating69 kmname match
Czech-Polish Interconnector Gas Pipeline (CPI)Proposed207 kmname match

Supplied via

Chokepoints that cargoes arriving at this terminal typically cross, based on where its region is supplied from.

  • Strait of Gibraltar
  • Suez Canal
  • Bab el-Mandeb
  • Danish Straits

Atlantic-basin supply from the United States crosses no chokepoint, which is why the European exposure figure is lower than it looks.

Routing is an editorial model of typical laden voyages, held in a hand-maintained lane table. It is not vessel tracking, and it does not account for diversions, canal draught limits, ice class or seasonal closures. See methodology, or take the machine-readable exposure feed. Links to the Chokepoints site are inactive until its domain is set in the environment.